Dallas ISD 2020 Bond — Still In Progress

The 33 Dallas ISD 2020 Bond projects that are NOT yet complete, 5+ years after voters approved the $3.7B bond. Red = stalled (no contractor assigned or TBD target opening), yellow = construction in progress with a set target. The 2026 bond asks voters for another $6.2B while much of the 2020 money remains unspent. Source: bond.dallasisd.org project tracking pages.

  • 2020-bond
  • dallas
  • accountability
  • schools
  • dallas-isd
  • bond
  • education
  • real_estate

Fields

NameFilledExample
name100%Harry C. Withers Elementary
address100%2959 Northaven Road, Dallas, TX 75229
contractor100%Gadberry
budget_display100%$17,000,000
status_category100%stalled
trustee_district100%1
architect97%Autoarch Architects
total_budget97%17000000
construction_status97%Ribbon-Cutting TBD Opening TBD
target_opening70%Fall 2025
trustee_name12%Byron Sanders District 5